Development plan status and plan preparation progression

The development plan in-force.
Action Date
Bridgend Local Development Plan adoption documents (2006 – 2021) Adopted 18 September 2013
Documents which supported the Local Development Plan’s preparation.
Action Date
Bridgend Local Development Plan introduction  (2006 – 2021) Formal preparation commenced 7 December 2005
Delivery Agreement and Sustainability Appraisal Scoping Report Consultation period 3 August – 8 September 2006
Delivery Agreement submitted to Welsh Assembly Government : 6 October 2006
Delivery Agreement agreed by Welsh Assembly Government : 6 November 2006
Sustainability Appraisal Scoping Report approved by Council: 28 December 2006
Candidate Sites / Site Register Call for sites 9 November 2006 to 31 January 2007

Candidate Site Register published 15 May 2007

LDP Vision & Strategic Growth Options Stakeholder Consultation 28 June – 10 August 2007
LDP Pre-deposit Proposals Consultation 12 February 2009 – 31 March 2009
Initial Consultation Report published 19 October 2009
Draft Candidate Site Assessment Procedure Consultation 23 October 2009 – 20 November 2009
Deposit Plan Consultation 4 July 2011 - 9 September 2011
Alternative Sites Consultation 28 October 2011 - 9 December 2011
Consultation Report Published 11 July 2012
Submission 31 July 2012
ExaminationAmended Sites Consultation August 2012 onwards
21 February 2013 – 9 April 2013
Inspector's Report Received 26 July 2013
Adoption 18 September 2013
A timetable summary of the Local Development Plan’s preparation.
Stage Date
Stage 1 - Review and develop evidence base for LDP April 2006 – July 2012
Stage 2 - Delivery agreement consultation period April 2006 – January 2007
August 2006 – September 2006
Stage 3 - Pre-deposit LDP participation and consultation period October 2006 – October 2009
January 2009 – March 2009
Stage 4 - Deposit LDP and feedback consultation period September 2009 – July 2012
July 2011 – September 2011
Stage 5 - Advertisement of ‘alternative sites’ consultation period October 2011 – December 2011
October 2011 – December 2011
Stage 6 - Submission and examination July 2012 – August 2013
Stage 7 - Inspectors report August 2013 – September 2013
Stage 8 - Adoption October 2013 – December 2013
Stage 9 - Annual monitoring report and review of LDP January 2014 onwards